Working With UK Power Networks

Thameslink F425 – Williams Way Depot Substation

The Summer of 2015 saw the arrival of the first of the new trains into the purpose built Three Bridges Depot at Crawley.

RJ Power Rail provided the most compelling offer, successfully secured the contract working on behalf of UK Power Networks for all the Electrical cable terminations and containment of the HV and DC cables within the new Williams Way Substation serving the new depot.

“I would like to take this moment in thanking RJ Power Group for all the works that they carried out for UK Power Networks at Williams Way Substation. We managed to achieve all key commissioning/energising dates with the various HV and DC switchgear installations within the Substation, which was mainly down to the support and the proactive attitude of RJ Power Groups team. The site management and on site work force were a credit to RJ Power Group throughout the time they were on site. They worked together with us on the cable management installation and design.

All the hurdles that were met along the way were approached with a positive attitude. UKPN have now handed the Substation over to the maintainer who were very happy with the finished product. Thanks again and I hope we will be working again together in the not to distant future.”

John Harkin, Site Manager, UK Power Networks (Rail Sector)

Project Deliverables

The works for UKPN within the new Williams Way Substation entailed:

  • Installation and Termination of HV Feeders cables F3007,F3008 and F3111
  • Installation and Termination of HV cables to new Auxiliary Transformers
  • Installation and Termination of DC Positive Track cables between DC Rectifiers and DC switch gear.
  • Installation and Termination of DC Positive Track Interconnector cables
  • Installation and Termination of DC Negative Track cables between DC Rectifiers and Negative Busbars
  • Installation and Termination of Negative Bonding and Isolation DC Track cables
  • Installation and Termination of Negative Reference cables
  • Sheath and Pressure Testing of the new HV Feeder cables F3007, F3008 and F3111
  • Assistance with Design and Installation of cable containment for the DC and HV cables
  • Jointing of HV Feeders Trackside

Challenges & Solutions

RJ Power Group worked with UKPN site management on the challenging task to ensure that the routing of the cabling between equipment met the required specification within the substation and did not conflict with other cabling required coming in from the depot or other cabling within the substation.

All commissioning dates were achieved to the programmed dates.

RJ Power Group are an experienced power solutions delivery provider who work collaboratively as a reliable and trusted partner with all of our clients, providing exceptional expertise and proven project delivery.

About Us

RJ Power Rail Limited is a Full Trackside Principal Contractor to Network Rail and provides power engineering services for the rail industry. Its expert team has decades of experience covering all aspects of electrical engineering within high voltage electrification systems, traction power and industrial low voltage distribution systems across various regions within the UK.

RJ Power Rail Limited shares our clients’ objectives in how we conduct ourselves and our business, which has allowed us to develop long-term relationships with both Network Rail, TfL and several Tier One contractors.